Ram Temple in Ayodhya: Construction of Ram temple going on fast, foundation filling will be completed by October

Highlights:

  • Ram temple construction is going on in Ramnagari. Till now, 5 layers have been prepared in the work of filling the foundation.
  • This work is expected to be completed by the month of October. After this the work of making 16 feet high plinth with red stones will start.
  • Till now, the work of foundation construction work is going on for the construction of Ram Janmabhoomi temple in 24 hours 2 shifts.
  • The foundation of Ram Janmabhoomi temple has been made 400 feet long, 300 feet wide, 50 feet deep.

Mayank Srivastava, Ayodhya
in Ramnagari Ram Mandir Construction continues. Till now, 5 layers have been prepared in the work of filling the foundation. This work is expected to be completed by the month of October. After this the work of making 16 feet high plinth with red stones will start. Giving information about this, Dr. Anil Mishra, Trustee of Shri Ram Janmabhoomi Teerth Kshetra Trust, said that till now the foundation construction work is going on for the construction of Ram Janmabhoomi temple in 24 hours 2 shifts. The foundation of Ram Janmabhoomi temple is 400 feet long, 300 feet long. wide 50 feet deep. The foundation of Ram Mandir is being filled with 44 layers. So far 5 layers have been prepared. The construction work of the sixth layer has started. A layer 12 inches thick is being made from engineering field material, which takes 4 to 5 days to make.

Red stone base platform of Mirzapur
Trustee Dr Anil Mishra informed that the work of filling the foundation for the construction of the temple would be completed by the month of October. After that the work of making 16 feet high plinth with red stones of Mirzapur will start. The plinth is the base platform of the Ram temple. Which will be built 16 feet high from the earth. Two different stones will be used in the construction of Ram Janmabhoomi temple. Red stones of Mirzapur Vindhyavasani Dham of Uttar Pradesh will be used for the base of Ram Janmabhoomi. Larsen & Toubro (L&T), engaged for the construction of Janmabhoomi, has also ordered the stones of Vindhyavasani Dham. These stones will start reaching Ayodhya after rain. To give a definite shape to these stones, carving work will be done by setting up a workshop in the Ram Janmabhoomi complex.

CM Yogi’s mega plan, preparation for vaccination of 10 crore people in the state between June and August
Pink stone will come from Rajasthan

Clarifying the matter, Trustee Dr Anil Mishra said that Pink Stone will be used after the base is built in the construction of Ram Mandir. Pink stones are being procured from Banshi Paharpur in Rajasthan. However, one lakh cubic feet of stones have been carved in the workshop. The work of transporting these stones from Ramghat workshop to Ram Janmabhoomi complex has also been done more than half.

Ram Temple in Ayodhya: Construction of Ram temple going on fast, foundation filling will be completed by October

Ram Temple in Ayodhya: Construction of Ram temple going on fast, foundation filling will be completed by October

.

Source link

Leave a Reply

Your email address will not be published. Required fields are marked *